Sparrow Pond Restoration
Location
Glencarlyn Park, off of the W&OD trail. Upslope from the Glencarlyn dog park.
Status
In Design
- Spring 2019 - Kickoff/30% Design
- Fall 2019 - 60% Design
- Winter 2021 - 90% Design
- 2021-2022 - 100% Design, Permitting and Procurement
- 2022-23 - Construction (6-9 months)
Thanks to all who attended the virtual Sparrow Pond community meeting on Thursday, February 4, 2021. To view the presentation PDF and recording, please see below.
- See plans for the sediment forebay, pond footprint, construction access, and planting plan
- Learn more about the water quality benefit and habitat features
- Provide input on the draft design
For questions or more information, please contact Lily Whitesell at lwhitesell@arlingtonva.us or 703-228-3042.
About the Project
Sparrow Pond was originally constructed in 2001-02. Over time, the pond has filled in with sediment. The restoration was identified as part of the 2012-13 Watershed Retrofit Study, and funding was allocated for design through the Capital Improvement Program in 2018.
The project goal is to restore the pond to the original depth by removing sediment, add a sediment collection forebay to allow easier maintenance and sediment removal, maximize water quality benefits, and restore habitat.
About the Process
Thanks to all who have participated in the public process so far. Please feel free to send comments, questions, or feedback to Lily Whitesell, lwhitesell@arlingtonva.us, 703-228-3042.
Date | Location and Description | Meeting Materials |
February 4, 2021 | Virtual Meeting, 90% Design Review and Provide Input | |
October 1, 2019 | Long Branch Nature Center, 625 S Carlin Springs Rd Review Updated Draft 60% Design |
|
March 14, 2019 | Carlin Hall, 5711 4th St S Kickoff Meeting and 30% Design Review |
|
February 7, 2019 | Barcroft House, 800 S Buchanan St Short Presentation at Civic Association Meeting - Brief Overview |