North Highland Street
Location
North Highland Street from Arlington Boulevard to 1st Road North (Lyon Park Neighborhood)
Status
Out to Bid
November, 2020 - Washington Gas will be upgrading the gas main lines and services to residents on N Highland St. Their work will extend from a few houses south of 1st St N to mid-block between 1st Rd N and 2nd St N. This project will commence in early to mid-November, and is anticipated to take 3 months to complete.
October 2020 - Procurement of a construction contractor for this project is underway.
October, 2020 - Relocation of utility poles was completed in October.
About the Project
- West side of the street: 4′-0″ wide concrete sidewalk adjacent to a 2′-6″ to 3’-0” utility (grass) strip, curb & gutter, with ADA compliant pedestrian ramps.
- East side of the street: new curb & gutter, ADA complaint curb ramp installed at the intersection with 1st Street N, tie in to existing sidewalk.
- Driveway aprons within the project limits will be replaced.
- Asphalt street reconstruction and pavement milling/paving.
- The roadway will be narrowed to 28’, except in the area of a significant tree, where the road width will further reduce to 22’. A small portion of the street closer to Arlington Blvd. will widen slightly to 28’’, and will maintain two travel lanes, one in each direction.
- On street parking will be retained on both sides, except where the road narrows adjacent to the large tree, and where prohibited for traffic engineering ordinance reasons.